CAPM & PMP Practice Questions – Set 2

1. Reserve Analysis a technique not used in: A. Estimate Costs B. Estimating Activity Duration C. Control Costs D. Determine Budget Answer: C Explanation: Reserve Analysis: Many cost estimators include reserves, also called contingency allowances, as costs in many schedule activity cost estimates. Reserve Analysis a technique not used in Control Costs. 2. A Project